[Author Prev][Author Next][Thread Prev][Thread Next][Author Index][Thread Index]

[or-cvs] r22383: {projects} update the project tracking file and pdf. (projects/todo)



Author: phobos
Date: 2010-05-24 21:52:57 +0000 (Mon, 24 May 2010)
New Revision: 22383

Modified:
   projects/todo/tpo-highlevel-tasklist.tjp
   projects/todo/tracking-gantt.pdf
Log:
update the project tracking file and pdf.


Modified: projects/todo/tpo-highlevel-tasklist.tjp
===================================================================
--- projects/todo/tpo-highlevel-tasklist.tjp	2010-05-24 07:17:42 UTC (rev 22382)
+++ projects/todo/tpo-highlevel-tasklist.tjp	2010-05-24 21:52:57 UTC (rev 22383)
@@ -52,7 +52,7 @@
   }
   task op_four "Main Website Overhaul" {
     start 2009-12-01
-    end 2010-05-01
+    effort 90d
     allocate andrew, vendor
     complete 80
   }
@@ -171,7 +171,7 @@
     start 2009-11-19
     effort 30d
     allocate carolyn, volunteer
-    complete 10
+    complete 100
   }
   task tr_four "Russian Translator" {
     start 2009-11-19
@@ -230,6 +230,12 @@
     allocate melissa
     complete 100
   }
+  task fin_five "2009 Audit" {
+    start 2010-03-01
+    effort 90d
+    allocate melissa, andrew, vendor
+    complete 75
+  }
 }
 
 task research_dev "Research" {
@@ -258,7 +264,7 @@
       start 2009-11-20
       effort 60d
       allocate karsten, roger
-      complete 30
+      complete 40
     }
   }
   task rd_three "NRL Research" {
@@ -382,7 +388,7 @@
     start 2009-12-07
     effort 14d
     allocate karsten
-    complete 75
+    complete 100
   }
   task m_five "Server Descriptor Aggregator" {
     start 2010-03-01
@@ -406,13 +412,13 @@
     start 2010-03-01
     effort 14d
     allocate karsten, andrew
-    complete 30
+    complete 100
   }
   task m_nine "Metrics Website Presentation" {
     start 2010-03-01
     effort 30d
     allocate volunteer, karsten, andrew
-    complete 10
+    complete 20
   }
 }
 
@@ -487,7 +493,7 @@
     start 2009-11-19
     end 2009-12-31
     allocate christian, carolyn
-    complete 80
+    complete 100
   }
   task gt_four "Internationalization" {
     start 2009-11-19

Modified: projects/todo/tracking-gantt.pdf
===================================================================
(Binary files differ)