[or-cvs] r21774: {projects} update progress on a number of tasks, bump a few tasks to fl (projects/todo)
Author: phobos
Date: 2010-03-01 02:30:02 +0000 (Mon, 01 Mar 2010)
New Revision: 21774
Modified:
projects/todo/tpo-highlevel-tasklist.tjp
projects/todo/tracking-gantt.pdf
Log:
update progress on a number of tasks, bump a few tasks to floating
effort rather than start and end dates, and finally update the pdf.
Modified: projects/todo/tpo-highlevel-tasklist.tjp
===================================================================
--- projects/todo/tpo-highlevel-tasklist.tjp 2010-02-28 06:03:42 UTC (rev 21773)
+++ projects/todo/tpo-highlevel-tasklist.tjp 2010-03-01 02:30:02 UTC (rev 21774)
@@ -1,4 +1,4 @@
-project TorProject "High-Level Task Tracking" "1.0" 2009-11-19 - 2010-12-31 {
+project TorProject "High-Level Task Tracking" "1.0" 2009-11-19 - 2011-06-01 {
# Hide the clock time. Only show the date.
timeformat "%Y-%m-%d"
weekstartssunday
@@ -52,9 +52,9 @@
}
task op_four "Main Website Overhaul" {
start 2009-12-01
- end 2010-03-31
+ end 2010-05-01
allocate andrew, vendor
- complete 10
+ complete 15
}
task op_five "Legal Directory" {
start 2009-11-19
@@ -72,7 +72,7 @@
start 2009-11-19
end 2010-02-15
allocate andrew, karen, vendor
- complete 50
+ complete 100
}
task op_eight "2010 Budget" {
start 2009-11-19
@@ -84,7 +84,7 @@
start 2009-11-19
end 2010-02-28
allocate andrew, karen
- complete 30
+ complete 75
}
task op_ten "Migrate wiki" {
start 2009-11-19
@@ -108,7 +108,7 @@
start 2009-11-19
end 2010-02-28
allocate karen
- complete 50
+ complete 75
}
task op_fourteen "2010 Donation Drive" {
start 2010-01-01
@@ -130,7 +130,7 @@
}
task op_seventeen "Facebook App for Relays" {
start 2009-11-19
- end 2010-01-31
+ effort 5d
allocate steven
complete 25
}
@@ -250,7 +250,7 @@
}
task rd_two_two "Tor metrics research" {
start 2009-11-20
- end 2010-12-31
+ effort 60d
allocate karsten, roger
complete 10
}
@@ -266,7 +266,7 @@
start 2009-11-20
end 2010-06-01
allocate roger, karsten, volunteer
- complete 25
+ complete 50
}
}
task rd_four "Performance Improvements" {
@@ -304,25 +304,25 @@
task rd_seven "Everyone as a Relay" {
task rd_seven_one "Blog post on thoughts" {
start 2009-11-19
- end 2010-01-31
+ effort 1d
allocate steven
complete 100
}
task rd_seven_two "Proposals from suggested defenses" {
start 2009-11-19
- end 2010-01-31
+ effort 30d
allocate steven
complete 0
}
task rd_seven_three "Everyone as a Bridge proposal" {
start 2009-11-19
- end 2010-01-31
+ effort 30d
allocate steven
complete 0
}
task rd_seven_four "Continuing Research into everyone as a relay" {
start 2009-11-19
- end 2010-05-01
+ effort 45d
allocate steven
complete 0
}
@@ -436,17 +436,17 @@
start 2009-11-19
effort 14d
allocate mike
- complete 50
+ complete 75
}
task lat_two "Connection rate limiting" {
start 2009-11-19
- end 2010-03-31
+ effort 14d
allocate mike
complete 0
}
task lat_three "Bandwidth Authority Improvements" {
start 2009-11-19
- end 2010-03-31
+ effort 14d
allocate mike
complete 0
}
@@ -488,25 +488,25 @@
task bridgedb "Bridge Database" {
task bdb_one "track bridge blocking by country" {
start 2009-11-19
- end 2010-01-31
+ effort 14d
allocate nick, christian
complete 0
}
task bdb_two "bridge assignment port diversity" {
start 2009-11-19
- end 2010-01-31
+ effort 14d
allocate nick, christian
complete 0
}
task bdb_three "web interface captchas" {
start 2009-11-19
- end 2010-01-31
+ effort 3d
allocate christian
complete 0
}
task bdb_four "implement email help command" {
start 2009-11-19
- end 2010-01-31
+ effort 5d
allocate christian
complete 0
}
@@ -535,13 +535,13 @@
start 2009-11-19
end 2010-02-28
allocate jacob, volunteer
- complete 75
+ complete 85
}
task mt_two "Tor on Maemo" {
start 2009-11-19
effort 30d
allocate jacob, volunteer
- complete 15
+ complete 100
}
task mt_three "Java Tor" {
start 2009-11-19
Modified: projects/todo/tracking-gantt.pdf
===================================================================
(Binary files differ)