[Author Prev][Author Next][Thread Prev][Thread Next][Author Index][Thread Index]
[or-cvs] r21517: {projects} update tasklist with current state. (projects/todo)
Author: phobos
Date: 2010-01-29 02:06:22 +0000 (Fri, 29 Jan 2010)
New Revision: 21517
Modified:
projects/todo/tpo-highlevel-tasklist.tjp
projects/todo/tracking-gantt.pdf
Log:
update tasklist with current state.
Modified: projects/todo/tpo-highlevel-tasklist.tjp
===================================================================
--- projects/todo/tpo-highlevel-tasklist.tjp 2010-01-28 23:30:00 UTC (rev 21516)
+++ projects/todo/tpo-highlevel-tasklist.tjp 2010-01-29 02:06:22 UTC (rev 21517)
@@ -66,7 +66,7 @@
start 2009-11-19
end 2010-01-31
allocate andrew, melissa, auditor
- complete 90
+ complete 95
}
task op_seven "Tor Logo Store" {
start 2009-11-19
@@ -88,7 +88,7 @@
}
task op_ten "Migrate wiki" {
start 2009-11-19
- end 2009-12-15
+ effort 5d
allocate andrew, volunteer
complete 50
}
@@ -102,7 +102,7 @@
start 2009-11-19
end 2010-01-31
allocate karen, carolyn
- complete 90
+ complete 100
}
task op_thirteen "Brochure" {
start 2009-11-19
@@ -244,7 +244,7 @@
task rd_two "NSF Research" {
task rd_two_one "NSF Contract" {
start 2009-11-20
- end 2009-12-31
+ end 2010-02-15
allocate roger, andrew, melissa
complete 75
}
@@ -274,7 +274,7 @@
start 2009-11-20
end 2010-02-28
allocate roger, nick
- complete 80
+ complete 100
}
task rd_four_two "Microdescriptor Proposal" {
start 2009-12-14
@@ -407,13 +407,13 @@
}
task tb_two "Integrate with private browsing" {
start 2009-11-19
- end 2010-01-31
+ end 2010-03-31
allocate mike
complete 10
}
task tb_three "Google Chrome Integration" {
start 2009-11-19
- end 2009-12-31
+ end 2010-03-31
allocate mike
complete 30
}
@@ -535,68 +535,68 @@
start 2009-11-19
end 2010-01-31
allocate jacob, volunteer
- complete 0
+ complete 15
}
task mt_three "Java Tor" {
start 2009-11-19
end 2009-12-31
allocate bruce
- complete 85
+ complete 90
}
}
task packaging "Packaging Improvements" {
task pkg_one "Vidalia as deb" {
start 2009-11-19
- end 2009-12-31
+ end 2010-01-20
allocate erinn
- complete 0
+ complete 100
}
task pkg_two "Vidalia as rpm" {
start 2009-11-19
- end 2009-12-31
+ end 2010-02-15
allocate erinn
- complete 0
+ complete 50
}
task pkg_three "torproject deb repo" {
start 2009-11-19
- end 2009-12-31
+ end 2010-01-20
allocate erinn, peter
- complete 75
+ complete 100
}
task pkg_four "torproject rpm repo" {
start 2009-11-19
- end 2009-12-31
+ end 2010-02-15
allocate erinn
complete 0
}
task pkg_five "Tor Browser Bundle for OS X" {
start 2009-11-19
- end 2010-01-31
+ end 2010-03-31
allocate erinn, jacob
complete 50
}
task pkg_six "Tor Browser Bundle for Linux" {
start 2009-11-19
- end 2010-01-31
+ end 2010-03-31
allocate erinn, jacob
complete 50
}
task pkg_seven "Nightly package builds" {
start 2009-11-19
- end 2010-01-31
+ end 2010-03-31
allocate erinn
complete 0
}
task pkg_eight "Vidalia Bundle for debian/ubuntu" {
start 2009-11-19
- end 2010-02-28
+ end 2010-03-31
allocate erinn
complete 0
}
task pkg_nine "Vidalia Bundle for centos/suse" {
start 2009-11-19
- end 2010-02-28
+ end 2010-03-31
allocate erinn
complete 0
}
Modified: projects/todo/tracking-gantt.pdf
===================================================================
(Binary files differ)