[or-cvs] r22383: {projects} update the project tracking file and pdf. (projects/todo)
Author: phobos
Date: 2010-05-24 21:52:57 +0000 (Mon, 24 May 2010)
New Revision: 22383
Modified:
projects/todo/tpo-highlevel-tasklist.tjp
projects/todo/tracking-gantt.pdf
Log:
update the project tracking file and pdf.
Modified: projects/todo/tpo-highlevel-tasklist.tjp
===================================================================
--- projects/todo/tpo-highlevel-tasklist.tjp 2010-05-24 07:17:42 UTC (rev 22382)
+++ projects/todo/tpo-highlevel-tasklist.tjp 2010-05-24 21:52:57 UTC (rev 22383)
@@ -52,7 +52,7 @@
}
task op_four "Main Website Overhaul" {
start 2009-12-01
- end 2010-05-01
+ effort 90d
allocate andrew, vendor
complete 80
}
@@ -171,7 +171,7 @@
start 2009-11-19
effort 30d
allocate carolyn, volunteer
- complete 10
+ complete 100
}
task tr_four "Russian Translator" {
start 2009-11-19
@@ -230,6 +230,12 @@
allocate melissa
complete 100
}
+ task fin_five "2009 Audit" {
+ start 2010-03-01
+ effort 90d
+ allocate melissa, andrew, vendor
+ complete 75
+ }
}
task research_dev "Research" {
@@ -258,7 +264,7 @@
start 2009-11-20
effort 60d
allocate karsten, roger
- complete 30
+ complete 40
}
}
task rd_three "NRL Research" {
@@ -382,7 +388,7 @@
start 2009-12-07
effort 14d
allocate karsten
- complete 75
+ complete 100
}
task m_five "Server Descriptor Aggregator" {
start 2010-03-01
@@ -406,13 +412,13 @@
start 2010-03-01
effort 14d
allocate karsten, andrew
- complete 30
+ complete 100
}
task m_nine "Metrics Website Presentation" {
start 2010-03-01
effort 30d
allocate volunteer, karsten, andrew
- complete 10
+ complete 20
}
}
@@ -487,7 +493,7 @@
start 2009-11-19
end 2009-12-31
allocate christian, carolyn
- complete 80
+ complete 100
}
task gt_four "Internationalization" {
start 2009-11-19
Modified: projects/todo/tracking-gantt.pdf
===================================================================
(Binary files differ)