[Author Prev][Author Next][Thread Prev][Thread Next][Author Index][Thread Index]

[or-cvs] r21030: {projects} add a slew of new tasks from recent meetings, update the pdf (projects/todo)



Author: phobos
Date: 2009-11-27 10:44:01 -0500 (Fri, 27 Nov 2009)
New Revision: 21030

Modified:
   projects/todo/tpo-highlevel-tasklist.tjp
   projects/todo/tracking-gantt.pdf
Log:
add a slew of new tasks from recent meetings, update the pdf to reflect
the changes


Modified: projects/todo/tpo-highlevel-tasklist.tjp
===================================================================
--- projects/todo/tpo-highlevel-tasklist.tjp	2009-11-27 12:36:29 UTC (rev 21029)
+++ projects/todo/tpo-highlevel-tasklist.tjp	2009-11-27 15:44:01 UTC (rev 21030)
@@ -57,7 +57,7 @@
     start 2009-11-19
     end 2010-01-31
     allocate andrew, volunteer
-    complete 5
+    complete 15
   }
   task op_six "Audit Prep" {
     start 2009-11-19
@@ -65,7 +65,7 @@
     allocate andrew, melissa, auditor
     complete 30
   }
-  task op_seven "T-shirt Store" {
+  task op_seven "Tor Logo Store" {
     start 2009-11-19
     end 2009-12-31
     allocate andrew, vendor
@@ -75,7 +75,7 @@
     start 2009-11-19
     end 2009-12-05
     allocate andrew, melissa
-    complete 50
+    complete 75
   }
   task op_nine "2009 Annual Report" {
     start 2009-11-19
@@ -87,7 +87,7 @@
     start 2009-11-19
     end 2009-12-15
     allocate andrew, volunteer
-    complete 20
+    complete 30
   }
   task op_eleven "December Board Meeting" {
     start 2009-11-19
@@ -131,6 +131,12 @@
     allocate steven
     complete 25
   }
+  task op_eighteen "Relay Advocacy" {
+    start 2009-11-19
+    end 2010-01-31
+    allocate jacob
+    complete 25
+  }
 }
 
 task tr_main "Translations" {
@@ -150,7 +156,7 @@
     start 2009-11-19
     end 2009-12-31
     allocate carolyn, volunteer
-    complete 0
+    complete 10
   }
   task tr_four "Russian Translator" {
     start 2009-11-19
@@ -293,13 +299,13 @@
     start 2009-11-19
     end 2009-12-07
     allocate karsten
-    complete 25
+    complete 40
   }
   task m_two "Metrics Portal Configuration" {
     start 2009-11-19
     end 2009-12-07
     allocate karsten
-    complete 25
+    complete 40
   }
   task m_three "Metrics Reporting" {
     start 2009-11-19
@@ -363,8 +369,144 @@
   }
 }
 
+task gettor "Get-tor email autoresponder" {
+  task gt_one "Farsi translation" {
+    start 2009-11-19
+    end 2009-12-04
+    allocate christian, jacob
+    complete 0
+  }
+  task gt_two "handle split packages" {
+    start 2009-11-19
+    end 2009-12-15
+    allocate christian
+    complete 50
+  }
+  task gt_three "Chinese translation" {
+    start 2009-11-19
+    end 2009-12-31
+    allocate christian, carolyn
+    complete 0
+  }
+  task gt_four "Internationalization" {
+    start 2009-11-19
+    end 2009-12-15
+    allocate christian
+    complete 25
+  }
+  task gt_five "Emailing executables via Gmail" {
+    start 2009-11-19
+    end 2009-12-31
+    allocate christian
+    complete 50
+  }
+}
 
+task bridgedb "Bridge Database" {
+  task bdb_one "track bridge blocking by country" {
+    start 2009-11-19
+    end 2010-01-31
+    allocate nick, christian
+    complete 0
+  }
+  task bdb_two "bridge assignment port diversity" {
+    start 2009-11-19
+    end 2010-01-31
+    allocate nick, christian
+    complete 0
+  }
+  task bdb_three "web interface captchas" {
+    start 2009-11-19
+    end 2010-01-31
+    allocate christian
+    complete 0
+  }
+  task bdb_four "implement email help command" {
+    start 2009-11-19
+    end 2010-01-031
+    allocate christian
+    complete 0
+  }
+}
 
+task mobiletor "Tor on mobiles" {
+  task mt_one "OrBot: Tor on Android" {
+    start 2009-11-19
+    end 2009-12-31
+    allocate jacob, volunteer
+    complete 75
+  }
+  task mt_two "Tor on Maemo" {
+    start 2009-11-19
+    end 2010-01-31
+    allocate jacob, volunteer
+    complete 0
+  }
+  task mt_three "Java Tor" {
+    start 2009-11-19
+    end 2009-12-31
+    allocate volunteer
+    complete 25
+  }
+}
+
+task packaging "Packaging Improvements" {
+  task pkg_one "Vidalia as deb" {
+    start 2009-11-19
+    end 2009-12-31
+    allocate volunteer
+    complete 0
+  }
+  task pkg_two "Vidalia as rpm" {
+    start 2009-11-19
+    end 2009-12-31
+    allocate volunteer
+    complete 0
+  }
+  task pkg_three "torproject deb repo" {
+    start 2009-11-19
+    end 2009-12-31
+    allocate volunteer
+    complete 75
+  }
+  task pkg_four "torproject rpm repo" {
+    start 2009-11-19
+    end 2009-12-31
+    allocate volunteer
+    complete 0
+  }
+  task pkg_five "Tor Browser Bundle for OS X" {
+    start 2009-11-19
+    end 2010-01-31
+    allocate volunteer, jacob
+    complete 50
+  }
+  task pkg_six "Tor Browser Bundle for Linux" {
+    start 2009-11-19
+    end 2010-01-31
+    allocate volunteer, jacob
+    complete 50
+  }
+  task pkg_seven "Nightly package builds" {
+    start 2009-11-19
+    end 2010-01-31
+    allocate volunteer
+    complete 0
+  }
+  task pkg_eight "Vidalia Bundle for debian/ubuntu" {
+    start 2009-11-19
+    end 2010-02-28
+    allocate volunteer
+    complete 0
+  }
+  task pkg_nine "Vidalia Bundle for centos/suse" {
+    start 2009-11-19
+    end 2010-02-28
+    allocate volunteer
+    complete 0
+  }
+}
+
 # A traditional Gantt Chart for the TaskJugglerUI
 taskreport "Gantt Chart" {
   headline "Project Gantt Chart"

Modified: projects/todo/tracking-gantt.pdf
===================================================================
(Binary files differ)