Hi there!
  * Size field: an estimation of how long you think it will take to get
    it done (not counting review time, just execution):
        * small < 1 day
        * medium < 1 week
        * large > 1 week
We have the "Points" and "Actual Points" fields for this. "Points" are
meant to be any unit of time appropriate for a given trac component, and
are the field for the estimate before work begins. "Actual Points"
specify the units of time the ticket actually took after completion, for
evaluation of estimate accuracy/drift/multiplier.

Popular choices for units of time for Points are "minutes", "hours", and
"days".

https://trac.torproject.org/projects/tor/wiki/org/process/TorAgileProcess


Yes, sorry for the mistake. Trac actually says points not size (used to Jira) I would suggest to stick with one type of 'measurement' unit so everyone can understand all the tickets. I don't mind following another

For 0.2.7 we did not go back to the tickets and updated the 'actual points' of it. Which we should do, and we will get there :)

And yes, sponsor field is not there yet (another mistake on my side) but you can add it as a keyword if you wish to. And we can fix that later :)








_______________________________________________
tor-dev mailing list
tor-dev@xxxxxxxxxxxxxxxxxxxx
https://lists.torproject.org/cgi-bin/mailman/listinfo/tor-dev

-- 
PM at TorProject.org
gpg fingerprint = 8F2A F9B6 D4A1 4D03 FDF1  B298 3224 4994 1506 4C7B
@isa

Attachment: signature.asc
Description: OpenPGP digital signature

_______________________________________________
tor-dev mailing list
tor-dev@xxxxxxxxxxxxxxxxxxxx
https://lists.torproject.org/cgi-bin/mailman/listinfo/tor-dev